Week5-6C: Foundations
Yesterday we poured 21 cubic yards of concrete (that’s two full trucks and 1 yard from a third) and marked the end of the pile phase of our foundations. From start to finish it took us 1 week of prep, inspections, and hard work. Next we’ll be working on the grade beams which will support the retaining walls of the house.
You can see the steel pipe sticking out of the fresh concrete. This is supporting the entire weight of the cage as the concrete cures. It will be removed after the pour is complete.On Wednesday we had our inspection of the cages with our building inspector. The process of pouring a concrete foundation involves several inspections from three different entities other than the contractor. They are:
2) A LA City licensed deputy inspector continuously checks the rebar ties and cages during their fabrication to insure they are correct size and configuration.
3) The Structural engineer checks the cages when they are out of the ground to insure they are correct size and configuration.
4) The building inspector checks the cages in the ground to make sure that the steel is not touching the soils and that the other three entities have signed off on the work.
5) Pour concrete and collect samples to be tested by the deputy inspector.
We flew through all of our inspections thanks to the hard work of Garcia Masonry. They’re work is exemplary and it got us off on the right foot with the city inspector.
I showed up on Monday morning to find a crane in the middle of the street. Since the piles are so large, we had to arrange for a crane service to lower them in. The operator from Garcia Crane Service (no relation to Garcia Masonry) nimbly maneuvered his boom in between the temporary power pole line and the main high-voltage line above the street, clearing the latter by a hair. The whole operation took about 2 hours with a crew of 4 on the ground to guide the pile cages into place. Since the borings are not perfectly straight the cages have to be pushed and pulled in order to get them into position. Before the crane releases the pile a 3’ length of 4” steel pipe is tucked into the area where the cage “daylights”. This is in order to hang the cage. Normally you would use 3” blocks of concrete called “dobies” that keep the steel off of the dirt. However, because of the extreme weight we had to hang them instead. 















